Wait of 35 weeks to bring vacant council houses back into use
Westmeath County Council are working to reduce the average time it takes to bring vacant council houses back into use, as the current turnaround period stands at approximately 35 weeks.
The figure emerged at the October meeting of Westmeath County Council, where councillors raised concerns about housing maintenance delays, the cost of refurbishing vacant properties and the shortage of larger homes for families on the transfer list.
Cllr Mick Dollard had asked how much vacant properties were costing the council to repair before they could be allocated to new tenants, while Cllr Paul Hogan questioned the length of time being taken to complete maintenance work.
Director of housing Ambrose Clarke told members that the council received €11,000 from central government towards the turnaround of each vacant property, while the average cost to the local authority was approximately €30,000. The council therefore have to meet the balance of the cost.
Mr Clarke said targets were in place to reduce the turnaround time, acknowledging that the current average of 35 weeks would have to come down.
Cllr Paul Hogan pointed to the figures in the management report, which recorded 2,448 housing repairs logged year to date, 1,899 repairs carried out and 1,392 outstanding repair requests. He asked whether some of the outstanding cases had been carried over from previous years, noting that additional money had been provided for housing maintenance.
Cllr David Jones also highlighted the difficulties experienced by tenants waiting for repairs. He cited the case of a constituent who had reported problems with the solar panels at a house he had moved into in February, but whose issue had still not been resolved despite repeated contacts.
Cllr Ken Glynn supported the concern, saying that while council staff were taking reports and passing them to contractors, the subsequent follow-up could take months.
Mr Clarke said the council were testing a new system, known as Adjust, which was intended to allow staff to track maintenance requests and establish where each job stood in the process. He hoped the system would be operational in the first quarter of 2027.
Under the existing arrangements, emergency repairs have a response time of 24 hours, urgent repairs five working days, while routine repairs are scheduled as resources allow. Planned works are subject to funding availability.
Mr Clarke acknowledged that the council did not currently have a system that allowed members to readily establish the progress of individual jobs without staff having to follow up with contractors.
The new system would allow the council to identify delays and prompt action where necessary, although Mr Clarke said additional staffing would also have funding implications.
Allocations and maintenance
Cllr Jones also questioned whether tenants in the Rental Accommodation Scheme (RAS) should be considered for social housing allocations in the same way as tenants receiving assistance under the Housing Assistance Payment (HAP).
Mr Clarke said the council’s allocation scheme treated RAS, short-term letting, long-term leasing and approved housing body accommodation as social housing. He said the existing arrangements reflected the allocation scheme approved in November 2025.
Members also sought an update on choice-based letting, which allows applicants to express an interest in available properties. Mr Clarke said the council intended to expand its use, particularly for properties that were proving difficult to allocate.
He explained that properties generally had to go through the normal offer-and-refusal process before being considered for choice-based letting, adding to the time taken to reallocate some homes.
Supported by the Local Democracy Reporting Scheme