Rail investment planned but key Mullingar project remains unfunded

There’s some good news on the horizon for users of the rail service between Mullingar and Dublin – but one of the biggest projects awaited does not yet have a start date or a budget, Minister Robert Troy has learned from Iarnród Éireann.

The rail company has written a comprehensive reply to Minister Troy on what measures are in the pipeline that will benefit service users, but it has admitted that there is as yet no funding in place for the double-tracking of the line between Maynooth and Mullingar.

“Under the All-Island Strategic Rail Review (AISRR), double-tracking of Maynooth to Mullingar, and additional sections of double-track known as ‘passing loops’ will facilitate both improved frequency and journey time. At this time, such works are not funded,” the company stated in a document written in response to Minister Troy’s request for an update on plans to enhance rail infrastructure and passenger capacity on the route.

Minister Troy said he was prompted to make the query following ongoing concerns raised by commuters regarding overcrowding and the need for more frequent services.

While the double-tracking project may be some way in the future, Iarnród Éireann said there are a number of shorter-term interventions which will generate additional capacity on the route.

The document stated that the company had witnessed record passenger demand in 2025, with more than 55 million journeys, a figure that is set to grow further in 2026.

“It is our ambition to continue to enhance capacity on our rail network to increase service frequency,” Iarnród Éireann stated.

The company explained that, under the Early Interventions detailed in the AISRR Prioritisation Strategy, published by the Department of Transport in December, a second platform and passing loop section of track is proposed at Enfield, targeted to be delivered by 2030, subject to funding.

In addition, the new DART fleet depot is set to be developed west of Kilcock, and the Railway Order application for this project is to be submitted before the end of this year.

That will also see double-track installed between Maynooth and Kilcock, “which will dramatically increase frequency of services, and will be delivered by high capacity DART services”.

The new DART trains are to begin entering service in 2027, which the company says will provide extra capacity on the network.

“In total, 285 carriages have already been ordered for the Greater Dublin Area.

“These will begin entering service from Q2 2027 onwards, with 50 carriages expected to enter service in 2027 and the remainder in 2028 and 2029, and we intend to place subsequent orders of this fleet.”

Continuing, the company stated that the first order of 95 carriages will directly benefit the Drogheda line (65 battery-electric carriages) and the existing DART (30 electric carriages).

That will also allow Intercity and Commuter trains currently operating on the Drogheda line to be used on other routes around the network.

“Their deployment will be subject to review with and the approval of the National Transport Authority, subject to demand and infrastructure capacity at the time.”

The process is to be repeated with the introduction of a further 90 battery-electric carriages, freeing up existing trains, while the remaining 100 electric carriages will ultimately replace the original DART fleet, which has been in operation since 1984.

“Furthermore, infrastructure works for DART+ West, which will allow more trains to operate on the route, are set to commence, with enabling works from 2027 onwards,” the reply concluded.

Welcoming the update, Deputy Troy said Mullingar is one of the fastest-growing commuter centres in the country and that it is essential rail services keep pace with that growth.

While he welcomed confirmation that “substantial investment is planned” which will increase capacity across the network and create opportunities for improved services on the Dublin-Sligo line, he remained mindful of the need for a funding commitment for the double-tracking of the line from Maynooth to Mullingar.

“While these short and medium-term measures are positive developments, I will continue to press for the delivery of the long-term infrastructure projects identified for this corridor.

“Double-tracking between Maynooth and Mullingar remains critical if we are to achieve the level of service frequency and journey time improvements that commuters deserve.