Concern over ‘slippery’ surface at Harbour Bridge
Safety concerns over the condition of the Harbour Street footbridge in Mullingar have prompted a commitment to seek funding for its rehabilitation in 2027, including the installation of a more slip-resistant surface.
The issue was raised by Cllr Ken Glynn at the November meeting of the Municipal District of Mullingar Kinnegad, following complaints that sections of the bridge decking were loose and that the surface became particularly slippery in wet and icy weather.
The District Office confirmed that loose decking boards had been repaired, but Cllr Glynn questioned whether the bridge was now sufficiently safe for pedestrians.
He said the complaints he had received related not only to the loose boards but also to the poor condition of the overall surface.
Pat Kavanagh, district engineer, said the bridge had been visually inspected and the loose boards tightened as part of routine maintenance. He acknowledged that the timber decking was probably 15 to 20 years old and might now need to be replaced.
He said the bridge had been included in the council’s 2027 bridge rehabilitation funding application, with the intention of looking at a more suitable, non-slip surface. "It’s probably just at its stage where it needs to be replaced in the next years," he said.
Greenpark
Cllr Glynn also asked the council to consider installing traffic-calming measures along a straight stretch of road in Greenpark Meadows. The District Office confirmed that traffic-calming works at the location would also be considered as part of the 2027 works estimates.